Ax3.ai
Home / News / The Ax3 take
Data Center DynamicsPowerSeptember 3, 2026

California passes 75 MW large-load tariff bills — new data center service from January 2027 pays its own way

California just told data centers over 75 MW that they will pay the full cost of their own grid connection. It won’t be the last state to do so — and every one that follows raises the value of a site where the power is already on.

The California legislature passed a package of data center bills this week, headlined by SB 886 (the California Technology Innovation and Ratepayer Protection Act, Sen. Steve Padilla) and AB 2383 (the Fair Share in Energy Act, Asm. Rick Chavez Zbur). Together they require separate electricity tariffs for new large-load customers with peak demand of at least 75 MW, covering transmission, distribution and generation costs, plus updated interconnection rules. The tariffs apply to customers taking service on or after January 1, 2027, and the CPUC must finalize the structure by July 1, 2027. Companion bills add energy-use reporting, annual water reporting and environmental review requirements.

SB 886 cleared the Senate 28–10 and the Assembly 49–7. Governor Newsom has until the end of September to sign or veto; he rejected similar water-reporting measures previously but has recently signalled openness to regulation. The Data Center Coalition opposed the package.

California is following a path already worn by Ohio, Texas and several PJM states: large-load tariffs, minimum-take commitments, and cost allocation that shifts grid upgrade risk from ratepayers to the data center. Combined with FERC’s show-cause orders to the RTOs on co-location and behind-the-meter generation, the direction of regulation is unambiguous — future power is getting more expensive and slower to secure.

The Ax3 take

What it means if you’re buying: Every new tariff regime widens the price gap between power on paper and power in the ground. A site with an energized interconnect, a signed utility agreement and a known rate carries none of the 2027 tariff risk; a greenfield with a queue position carries all of it. Buyers who need capacity in the next 12–18 months should be underwriting energized megawatts, flowing today, in states that have not yet moved — and should expect those sites to reprice upward as more legislatures follow California.

What to do about it: That’s the thesis behind our powered-site book. ALTAIR 12 (~12 MW connected and flowing, ~5¢ industrial rate, SW Kansas), RIGEL 24 (24 MW metro site, 16 MW flowing today), PERSEUS 20 (20 MW existing with a gas expansion path) and PROCYON 24 (24 MW contracted, transferable) are all energized or contracted now. For larger builds, HYDRA (60 MW, West Virginia, 85 MW utility power at the initial site) and PHOENIX (50 MW, Kentucky) sit in markets without a large-load tariff on the books. Sellers holding energized capacity in a non-tariff state: this is the week to list it.

More from the Pulse

Related coverage

NVIDIA Newsroom NVIDIA Aug 26, 2026

AWS and NVIDIA commit 2 million more GPUs for 2027–2028

The largest single allocation headline of the year: two million Blackwell Ultra, Rubin and Rubin Ultra GPUs land at AWS across 2027–28, on top of the million-plus already committed. The queue for everyone else just got longer.

Data Center Dynamics Datacenter Sept 3, 2026

Michigan miner flips to neocloud tenant — 20 MW by Q4, lease worth up to $1.2B

Hyperscale Data shut down mining at its Dowagiac site on September 1 to prepare for a California neocloud: 20 MW live by Q4 2026, scaling to 52 MW, on a 10-year lease with two 5-year extensions. This is the deal template of 2026, with public numbers on it.